Deep beneath Brisbane is an engineering project conceived when the city still depended heavily on backyard toilets, sanitary workers and horse-drawn night carts. More than a century later, the S1 Main Sewer remains one of the most important pieces of infrastructure in Brisbane, carrying wastewater through the inner city towards the major network leading to Luggage Point.
The remarkable part of the story is not simply that such an old sewer survives. The S1 currently services more than 60 per cent of Brisbane, with sections of the main reaching about 1.5 metres in diameter and lying many metres below streets that have been completely transformed since the sewer was constructed. Modern Brisbane has effectively grown around an underground system whose basic form was conceived before the First World War.
Behind that system was an engineer who deserves a far more prominent place in Brisbane’s history. Gordon Thom arrived as the newly appointed Sewerage and Drainage Engineer and in 1911 developed the outline of an ambitious sewerage scheme stretching from Toowong across the city to Eagle Farm and onwards to a treatment works at Luggage Point. His plan used gravity wherever possible, deliberately taking the sewer progressively deeper as it travelled towards the mouth of the Brisbane River.
Building it required miners, deep shafts, compressed air, pumps, concrete, an electric construction railway, temporary power infrastructure and years of difficult work through unstable and waterlogged ground. Contracts failed, sections were abandoned and redesigned, senior engineers clashed and the problems eventually contributed to a Royal Commission.
Yet the fundamental idea endured. Brisbane’s first reticulated sewerage service followed, the network spread slowly through the suburbs, and the city eventually left behind a sanitation system that had required workers to physically remove human waste from tens of thousands of properties. The history of Brisbane’s main sewer is therefore as much about Gordon Thom, the engineers and the workers who built it as it is about the enormous pipe beneath the city.
Brisbane Had Spent Decades Trying To Solve Its Sanitation Problem
Brisbane became a municipality in 1859 without a comprehensive sewerage system. As the settlement expanded, the disposal of human waste became an increasingly serious public health and municipal problem.
Early drainage works primarily moved rainwater away from streets and developed areas. Open channels, creeks and later constructed drains carried stormwater towards the Brisbane River, but household sewage required a different system. Cesspits and earth closets were common, followed by increasingly organised sanitary collection services in which waste was stored in removable pans.
The familiar backyard toilet became part of Brisbane domestic life. Sanitary workers entered properties, removed the pans and carried them to collection vehicles. The contents ultimately had to be taken to depots, buried, transferred into other systems or transported elsewhere for disposal.
Brisbane had considered larger sanitation solutions long before construction of the main sewer began. Drainage and sanitation conferences were being held during the nineteenth century, but the metropolitan area was divided among numerous local authorities with different finances, priorities and boundaries. A sewerage network could not sensibly be planned as a collection of unrelated municipal projects.
By the beginning of the twentieth century, Brisbane needed an authority capable of looking at the metropolitan area as a whole.
A New Board Finally Had The Power To Plan Across Brisbane
The Queensland Government established the Metropolitan Water and Sewerage Board in December 1909, bringing metropolitan water and sewerage responsibilities under a single authority. Its appointed president was Ernest James Theodore Manchester, a Melbourne water engineer, while eight elected members represented the different local government areas.
The creation of the Board was a crucial administrative change. Before Greater Brisbane was formed, the metropolitan area consisted of numerous municipalities and shires. The new authority could plan infrastructure according to where water and sewage actually needed to travel rather than allowing local government boundaries to determine the shape of the network.
It was into this organisation that Gordon Thom arrived as Sewerage and Drainage Engineer.
Thom already had experience with the difficult questions surrounding sewage disposal. Immediately before his Brisbane work, G. W. Thom was engineer to the Drainage Board in Hobart, where in 1910 he was reporting on sewage treatment and disposal. Brisbane had therefore recruited an engineer whose professional attention was already focused on the problem the city urgently needed to solve.
Within a relatively short period, Thom produced the outline that would shape Brisbane’s first major sewerage system.
Gordon Thom’s 1911 Plan Established Brisbane’s Sewerage Backbone
Thom’s 1911 scheme proposed a main sewer beginning around Toowong, running across the metropolitan area to Eagle Farm and receiving wastewater from a series of branch sewers along the way. From Eagle Farm, the main would continue towards a treatment facility near the mouth of the Brisbane River at Luggage Point.
The scale of the proposal becomes clearer when Brisbane at the time is considered. The modern CBD skyline did not exist, motor vehicles were still relatively uncommon, many present-day suburbs remained sparsely developed and the eastern reaches around Pinkenba and Luggage Point were dramatically different from the industrial and airport landscape seen today.
Thom was planning infrastructure not only for the Brisbane in front of him but for a city expected to become much larger.
One of his most important decisions concerned gravity. Pumping sewage continuously across Brisbane would require expensive machinery, energy and ongoing maintenance. Thom instead designed a low-level system that would allow gravity to carry sewage for much of the journey.
That decision explains one of the most striking characteristics of the original scheme. As the sewer travelled towards Luggage Point, it went progressively deeper. Near the treatment works, the sewage would arrive at almost 50 feet below mean sea level, roughly 15 metres beneath that reference level. A major pumping shaft could then raise it to the surface for treatment.
The depth was therefore not an accidental consequence of construction. It was central to Thom’s engineering philosophy for the system. Gravity would perform much of the transport work, with major pumping concentrated where it was necessary.
Thom Used Brisbane’s Roads To Create An Underground Corridor
The proposed main sewer generally followed road reserves where practical. This gave construction crews access to the route and reduced the need to obtain underground rights through large numbers of privately owned properties.
The compromise was that the sewer could not always take the shortest possible route. Streets and property boundaries had already shaped the city above ground, and Thom’s underground network had to work within that environment.
Following road reserves also meant that construction difficulties could become problems for the road itself. Deep shafts had to be sunk from the surface, tunnels driven between them and enormous amounts of material moved into and out of the excavations. When the ground moved or shafts encountered trouble, the effects were not necessarily confined underground.
Modern Brisbane residents travelling above parts of the S1 are following streets whose relationship with the sewer reaches back to these original planning decisions.
Luggage Point Was An Extraordinary Place To Build A Treatment Works
Choosing Luggage Point made sense as part of a metropolitan sewerage scheme, but reaching and building on the site presented enormous practical difficulties.
In the 1910s, Luggage Point was far removed from urban Brisbane. Pinkenba itself was near the edge of substantial development, and the proposed treatment works lay several kilometres farther out through Myrtletown. The surrounding landscape included mangroves, tidal flats, farms and market gardens. Many of the gazetted roads were poorly formed, while parts of the treatment works site were vulnerable to tidal inundation.
A conventional road construction supply chain was therefore difficult. The sewer project needed rails, concrete materials, timber, coal, excavation machinery and enormous quantities of other supplies delivered to shafts and construction sites spread across the area.
The solution was almost a major infrastructure project in its own right.
They Built An Electric Railway To Help Build The Sewer
The works included a temporary two-foot-gauge light railway extending about 4¾ miles through the Pinkenba, Myrtletown and Luggage Point area. It provided access to sewer shafts and carried construction materials through country where dependable all-weather roads were lacking.
The railway used electric traction. A temporary powerhouse was established at Myrtletown, with electricity distributed along the construction route. The same electrical system could support far more than the locomotives, supplying equipment associated with excavation, cranes and haulage at the sewer works.
A wharf allowed construction materials to arrive by water. Sand, gravel, coal, cement, machinery and other supplies could then be distributed through the work sites, while excavated material could be transported where it was required for filling and construction.
As work intensified, the railway became increasingly busy. A second electric locomotive was eventually acquired to help deal with the volume of traffic.
It is an extraordinary part of Brisbane history that has almost completely disappeared from the modern landscape. An electric industrial railway once ran through an area now dominated by Brisbane Airport and industry because the engineers building the city’s sewer needed their own transport network to reach it.
The Men Underground Were Effectively Working As Miners
The physical construction of the sewer was very different from modern tunnel building. Large sections were excavated by workers using mining techniques, with shafts sunk from the surface and tunnel drives extending between them.
The legal status of the work reflected the conditions underground. Amendments made during construction treated main sewer shafts and tunnels as mines for important purposes. Workers involved in underground sewer construction consequently had to be paid at mining rates, while supervision became subject to requirements associated with certified mine managers.
That created complications of its own. Experienced sewerage engineers understood the design and construction requirements of the project, but mine-management certification depended on substantial underground mining experience. The result could place engineering direction and statutory underground supervision in different hands.
The work itself could be exceptionally difficult. Shafts encountered groundwater, tunnel faces became unstable and some sections required compressed air so workers could continue excavating through saturated ground. Pumps had to operate to hold back water, timbering or other support was required to prevent collapse, and concrete construction followed behind the excavation.
The S1 is sometimes described simply as an old concrete sewer. That description gives little sense of what creating it actually required. Before the concrete lining existed, men had to descend shafts and drive a tunnel beneath Brisbane using the methods available to early twentieth-century miners.
The Ground Near Pinkenba Fought The Project Almost Every Step Of The Way
The low-level design encountered its greatest difficulties as construction moved through the soft and waterlogged country around Pinkenba and Luggage Point.
By 1916, some shaft excavations were experiencing serious problems with waterlogged ground. Compressed-air tunnelling became necessary in places, increasing both the complexity and cost of the work. Sections were suspended, shafts were abandoned and alternative approaches had to be considered.
The difficulties were compounded by the First World War. Labour and materials became more expensive and harder to obtain, while industrial disputes added further delays. One contract covering a section towards Hamilton encountered severe ground problems, subsidence and increasing costs before being abandoned in 1916, followed by legal action between the contractor and the Board.
Some of the conditions encountered later were described as being among the worst tunnelling ground experienced in Australia. Progress could fall to little more than ten feet a week. In one section, a surveying error resulted in a tunnel being driven almost three feet too high, requiring about 170 yards of work to be reconstructed.
The difficulties demonstrate the difference between designing a line across a map and physically creating it beneath an unpredictable river city. Thom’s overall concept was sound enough to shape Brisbane’s sewerage future, but translating that concept into concrete underground infrastructure proved much harder than expected.
The Original Low-Level Route Had To Be Abandoned In Places
By 1918, the Board accepted that parts of the original low-level route towards Luggage Point could not practically be completed as first intended. A higher-level sewer was adopted for part of the route, with additional pumping required to lift sewage from the deeper system into it.
The change sacrificed some of the purity of the original gravity concept in exchange for a route that could actually be constructed through the conditions encountered on site.
A further deviation was developed for another troubled section between Pinkenba and the Hamilton direction. Experienced tunnelling engineer G. H. Dunlop was brought in to supervise that work, using a tunnelling shield and his own approach to timber support.
The decision also reveals increasing tension inside the sewerage project. Surviving Board records indicate that president Ernest Manchester had developed concerns about Thom’s management of some construction work. Rather than placing the deviation directly under the Sewerage Engineer, the Board accepted Dunlop’s offer to undertake it with a financial incentive linked to completing the work within a specified period.
Dunlop then encountered many of the same underlying problems that had frustrated earlier work. Shafts filled with water, river water entered excavations, ground subsided and tunnelling remained extremely difficult. Engineering disagreements were accompanied by arguments over materials, railway trucks, supply arrangements and who was responsible for delays.
The project had become not only an engineering challenge but an organisational one.
Gordon Thom Became Caught In The Project’s Internal Disputes
The tension did not disappear as construction continued. In 1920, responsibility for some of the Luggage Point works was divided between senior officers Alfred Upton and E. J. Corless. Upton took responsibility for the outfall sewer, powerhouse and electric railway operations, while Corless was placed in charge of the high-level sewer and reported directly to the Board.
The arrangement reduced the extent to which everything flowed through Thom as Sewerage Engineer and appears to have been poorly received by him and Upton.
Arguments followed over the allocation of railway trucks and the movement of construction materials. Corless complained that he could not obtain enough trucks and supplies to maintain progress on his section. Upton had competing demands because the same railway system was supplying other works. Board members repeatedly had to intervene in matters that reached into the day-to-day logistics of construction.
These disputes should not obscure the scale of the challenge facing everyone involved. The project was trying to coordinate deep tunnelling, pumping, concrete manufacture, electric rail operations, wharf deliveries, treatment-works construction and multiple contractors across difficult terrain during and immediately after a world war.
Still, the accumulation of delays and difficulties became serious enough that a Royal Commission was conducted in 1921 by C. E. Oliver into the construction of the sewer.
Brisbane’s first sewerage scheme was therefore far from a straightforward public works triumph. It was an ambitious project that repeatedly had to be altered, rescued and pushed forward by engineers and workers dealing with problems that its original planners could not fully have anticipated.
The Sewer Was Finally Becoming A Working System
Despite the setbacks, the main sewer gradually came together. Difficult sections around Pinkenba were completed during the early 1920s, with the final short portion associated with the main works finished in March 1923.
Brisbane’s first sewage treatment plant at Luggage Point officially opened on 23 November 1923, marking a fundamental change in the way the city could manage human waste. The broader reticulated system continued to be developed and connected through the following years.
The red-brick industrial buildings that survive at Luggage Point provide one of the few substantial above-ground reminders of this period. Most of the achievement immediately disappeared from view because the principal infrastructure was buried beneath streets and land.
For households connected to the new system, the change was profound. A flushing toilet could discharge into local pipes that fed larger sewers and eventually the metropolitan network. Human waste no longer needed to be stored behind the house waiting for somebody to physically collect it.
Yet Brisbane was nowhere near fully sewered.
The Night Carts Continued Beside Thom’s New Sewer
The arrival of reticulated sewerage created two Brisbanes that existed alongside each other for decades. Central and inner areas progressively connected to the network, while extensive suburban districts continued using earth closets and sanitary collection.
Night-soil workers remained essential municipal workers. They entered properties, removed filled pans from backyard toilets and replaced them with clean containers. Access through the property mattered, which helps explain some of the narrow side passages, rear toilet positions and service arrangements found on older Brisbane allotments.
Sanitary depots were located around the metropolitan area rather than all of Brisbane’s waste being carried to one central destination. The former Lota Sanitary Depot provides a surviving example, with facilities that included stables, garages and areas associated with the disposal operation.
At Milton, collected night soil was eventually introduced into the sewerage system itself before continuing towards Pinkenba. Earlier city arrangements had included sanitary facilities near North Quay and the transport of waste by water.
The northside had its own local history. A large manure depot operated at Bracken Ridge near the Telegraph Road district and served the Sandgate area. Horse-drawn sanitary vehicles brought waste to the depot before motor vehicles took over. The presence of the depot remained embedded in the local landscape through names such as Depot Road long after the original sanitation system disappeared.
These depots show how enormous the transition to sewerage really was. Brisbane was not simply laying pipes. It was gradually dismantling an entire parallel industry involving workers, horses, vehicles, depots, cleaning facilities and disposal sites.
Brisbane Was Still Heavily Dependent On Night Carts Decades Later
The old system survived for an extraordinary length of time. Historical accounts record night-cart services covering around 80 per cent of Brisbane’s area as late as 1961.
That figure refers to the geographic extent in which sanitary collection still operated and should not be interpreted to mean that 80 per cent of every Brisbane household lacked sewerage. Many central and established areas had been connected for decades. It nevertheless demonstrates how much of the expanding metropolitan area still required the older service.
For families in those suburbs, the night cart was not distant colonial history. It was part of ordinary life during the post-war era.
The contrast with Thom’s 1911 plan is striking. Half a century after he had designed a metropolitan sewer stretching from Toowong towards Luggage Point, the infrastructure he helped establish was carrying sewage beneath Brisbane while sanitary workers were still manually removing pans from homes elsewhere in the same city.
The 1940 Pinkenba Collapse Added Another Serious Problem
The network also suffered a major failure when a sewer collapsed at Pinkenba in 1940. The incident came after years in which expansion had already been constrained by the economic effects of the Great Depression and was followed by the extraordinary demands of the Second World War.
Brisbane became a major Allied centre during the Pacific conflict. Its population and military presence placed intense pressure on accommodation, roads, transport, water and other municipal services at a time when resources for large civilian infrastructure projects were restricted.
The result was that sewerage continued to spread, but not at anything like the speed required to eliminate the sanitary collection system across the rapidly expanding metropolitan area.
Post-war suburban growth made the challenge larger again. New houses were spreading farther from the old inner-city sewered districts at exactly the time Brisbane needed to catch up on infrastructure that had already been delayed for decades.
Clem Jones Did Not Start Brisbane’s Sewerage System, But He Helped Finish The Transformation
The name most strongly associated with sewering modern Brisbane is Clem Jones, who became Lord Mayor in 1961 and remained in office until 1975. Jones deserves an important place in the story, although his role was very different from Gordon Thom’s.
By the time Jones became Lord Mayor, Thom’s original metropolitan system had existed for decades. The main sewer, pumping infrastructure and Luggage Point treatment works were already established, while substantial areas of the inner city had long been connected.
What remained was the enormous job of extending sewerage through the suburban city that Brisbane had become.
Jones was a qualified surveyor and town planner and came to office at a time when Brisbane required major investment in roads, drainage, water and sewerage. His administration drove a large acceleration of infrastructure works during the 1960s and early 1970s, pushing the sewer network into areas that had continued relying on night-soil collection.
The effect was dramatic. From night-cart services still operating across large portions of Brisbane in 1961, the number of houses requiring night-soil collection had fallen to fewer than 5,000 by 1973-74.
Individual districts progressively left the old system behind. Sewerage works in areas such as Wynnum and Manly removed the need for local sanitary depots, while similar projects transformed suburbs across Brisbane.
Jones therefore did not originate the sewerage system, but his period as Lord Mayor was crucial to completing the transition that Gordon Thom and the Metropolitan Water and Sewerage Board had started half a century earlier.
Luggage Point Changed Along With Brisbane
The treatment end of the system also evolved substantially. The standards applied to sewage treatment during the 1920s bear little resemblance to those expected from a modern wastewater facility.
Early operations at Luggage Point reflected the knowledge, environmental expectations and technology of their era. Problems associated with pollution near the mouth of the Brisbane River became increasingly apparent, including a serious typhoid scare in the 1930s associated with oysters harvested near the sewerage outlet.
As Brisbane grew and environmental standards improved, the treatment works had to change with it. Major new works commenced during the 1970s, while subsequent upgrades progressively transformed Luggage Point into a modern wastewater treatment and resource recovery facility.
The location selected during the development of Thom’s original scheme nevertheless remained central to Brisbane’s wastewater network more than a century later.
The S1 Continued Working As Brisbane Grew Above It
The survival and continued importance of the S1 is remarkable because virtually everything above it has changed.
The Brisbane for which Gordon Thom prepared his 1911 scheme was a relatively small, low-rise city. Greater Brisbane did not yet exist as a single council. The Story Bridge had not been built, Brisbane Airport occupied an entirely different form, suburban development had not spread anywhere near its modern extent and the road system carried only a fraction of present-day traffic.
During the sewer’s life, tramways expanded and disappeared, motorways were constructed, industrial districts changed use, high-rise buildings transformed the inner city and Brisbane’s population multiplied.
The wastewater load increased with all of it.
Urban Utilities describes the S1 as Brisbane’s largest and oldest main sewer and says it currently services more than 60 per cent of the city. The main is up to about 1.5 metres in diameter, with sections lying several storeys beneath modern Brisbane streets.
The basic underground corridor developed from an early twentieth-century sewerage plan therefore remains fundamental to a twenty-first-century city.
Engineers Eventually Had To Renew A Sewer Brisbane Could Not Do Without
Age inevitably created a new engineering challenge. A major sewer carrying such a large proportion of Brisbane’s wastewater cannot simply be switched off for months while crews dig it out and replace it.
Conventional excavation would also have caused enormous disruption along major urban roads, including sections around Fortitude Valley, Hamilton and Kingsford Smith Drive.
Modern engineers instead rehabilitated substantial sections from inside the existing sewer. A long program beginning in 2015 renewed kilometres of the S1 between Fortitude Valley and the Eagle Farm pumping station.
The work involved installing a new structural lining inside the old sewer. Continuous PVC material could be wound into place and reinforced where necessary, with grout filling the space between the liner and the existing structure. The result was effectively a renewed sewer created within the old one.
Much of the work was carried out at night. Crews entered through existing access points, established specialised equipment, completed work during restricted overnight periods and cleared major roads again before daytime traffic returned.
The contrast with Gordon Thom’s era could hardly be greater. The original system required miners, shafts, temporary railways, steam equipment, compressed air and early electric machinery. A century later, engineers returned to the same underground system with specialised liners, modern materials and equipment designed to renew it without excavating kilometres of the city above.
Gordon Thom’s Influence Is Still Beneath Brisbane
Brisbane has many historical figures whose work remains visible. Bridges, roads, parks and buildings can carry the names of politicians, architects, engineers and civic leaders. Gordon Thom left something far less obvious.
His 1911 sewerage plan helped determine how Brisbane would move sewage across the city and towards Luggage Point. The project changed substantially during construction, difficult sections were redesigned and later generations expanded the network far beyond anything built during his immediate involvement. He also became caught in the disputes and frustrations of a project that proved vastly more difficult to construct than its drawings could convey.
That makes his story more interesting rather than less. Thom was not a figure who simply produced a flawless plan that workers then followed without difficulty. He proposed an ambitious engineering solution, saw parts of it collide with some of the worst tunnelling conditions the project could encounter, dealt with wartime shortages and organisational conflict, and watched other engineers take control of sections when the Board lost confidence in aspects of construction management.
Yet the central concept survived those difficulties. A low-level metropolitan sewer crossed Brisbane, branch systems fed into it, wastewater travelled east towards Luggage Point and the resulting infrastructure became the backbone from which a much larger network developed.
Most Brisbane residents will never see the S1. They can drive above it, live near it or pass over its route every day without knowing that one of the city’s most important pieces of infrastructure is below them.
More than a century after Gordon Thom sat down to plan a sewerage system for a Brisbane that looked almost nothing like the city of today, the engineering legacy of that decision is still carrying an extraordinary share of Brisbane’s wastewater.
The S1 is therefore more than an old sewer. It is the surviving backbone of one of the projects that allowed Brisbane to become a modern city, created by engineers and workers whose achievement has spent most of its existence hidden underground.
This article’s stylistic feature image is an artist’s impression and has been adjusted for aesthetic purposes; the sewer’s depicted size and location are not technically accurate.
You might also like
Disclaimer: Every effort has been made to ensure the accuracy of the information provided, but we make no guarantees regarding its completeness or reliability. The data is presented for general informational purposes only and does not constitute financial, investment, or legal advice. We are not liable for any errors, omissions, or consequences arising from its use. Users should verify details with relevant sources and seek professional advice where appropriate for the most accurate and up-to-date guidance.